D-PCI CONSTRUCTION PROCESS

Scope of Supply, Installation and Permanent Fixing of Padel Court Structures

Supply, Installation 

The Contractor (Dolan PCI Padel Courts) shall supply and install permanently fixed panoramic padel court structures at the Client site, forming part of the immovable sporting facilities. The Works shall include, but shall not be limited to:

  • Site set-out and court positioning

  • Installation of permanent steel court framework

  • Installation of structural glass panels

  • Fixing of all court structures to concrete ring beams and/or foundations prepared by or on behalf of the Client

  • Installation of artificial playing surface systems

  • Installation of lighting columns and flood lighting systems

  • Installation of access doors, net systems and ancillary fittings

  • Final alignment, testing, commissioning and handover

All padel court structures shall be permanently affixed to the Client’s site and shall form part of the immovable property upon completion.

Firefly (1).png
Firefly_Gemini Flash_create a photography illustrating Pre-Construction & Groundworks Supp

Pre-Construction & Groundworks Support

Upon receipt of the 10% deposit or a site visit nominal fee (later deducted from court order), Dolan PCI will allocate a dedicated technical representative to the project.

From this stage, our technician will liaise directly with the Client's appointed groundworks contractor and/or construction team, providing technical guidance throughout the preparation of the site for the padel courts.

This support will include:

  • Review of court positioning, dimensions and site set-out

  • Provision and review of the required groundworks and foundation drawings

  • Liaison with the Client's contractor throughout the groundworks programme

  • Technical guidance regarding ring beams, foundations, drainage, ducting and electrical requirements

  • Review of finished levels, tolerances and court falls

  • Site visits by Dolan PCI at key stages of the groundworks

  • Identification of any issues or deviations before the court installation commences

  • Final inspection of the prepared court area prior to installation

The purpose of this process is to ensure that the groundworks are completed fully in accordance with Dolan PCI's technical requirements and to our satisfaction before installation of the courts begins.

Correct ground preparation is fundamental to the long-term performance of a padel court. In particular, drainage, levels, foundations and surface preparation are every bit as important as the specification and quality of the padel court itself.

The Client may appoint its own preferred groundworks contractor. Alternatively, Dolan PCI can arrange for contractors with whom we have previously worked to be invited to tender for the project.

Regardless of which contractor is ultimately appointed, Dolan PCI will apply the same technical monitoring and inspection process throughout the groundworks stage.

Foundations & Permanent Fixing

The Client confirms that suitable concrete ring beams and/or foundations shall be provided in accordance with the Contractor’s specifications. The Contractor’s installation shall involve permanent mechanical fixing of the padel court structures to these foundations. The Client acknowledges that portability or temporary installation is expressly excluded from this Agreement.

Firefly_image to illustrate the below text_Foundations & Permanent Fixing_____The Client c